Close Menu
  • News
  • Industry
  • Solar Panels
  • Commercial
  • Residential
  • Finance
  • Technology
  • Carbon Credit
  • More
    • Policy
    • Energy Storage
    • Utility
    • Cummunity
What's Hot

8MSolar vs. Southern Energy Management: Which NC Solar Installer Is Right for You? (2026)

March 9, 2026

Fixed grid dates for solar energy development in Britain are beginning to emerge

March 9, 2026

Midsummer secures second order for CIGS production line equipment

March 9, 2026
Facebook X (Twitter) Instagram
Facebook X (Twitter) Instagram
Solar Energy News
Monday, March 9
  • News
  • Industry
  • Solar Panels
  • Commercial
  • Residential
  • Finance
  • Technology
  • Carbon Credit
  • More
    • Policy
    • Energy Storage
    • Utility
    • Cummunity
Solar Energy News
Home - News - Fixed grid dates for solar energy development in Britain are beginning to emerge
News

Fixed grid dates for solar energy development in Britain are beginning to emerge

solarenergyBy solarenergyMarch 9, 2026No Comments6 Mins Read
Facebook Twitter Pinterest LinkedIn Tumblr Email
Share
Facebook Twitter LinkedIn Pinterest Email

The UK solar market remains busy, but for very different reasons than this time last year.

Of notifications about grid connections were issued four months ago nowand final dates are finally given to developers, buildouts can finally take place, and developers can connect projects that were mechanically completed up to twelve months ago.

More than 4GWp is currently being built in the country. Some developers have continued with ‘business as usual’ – a risk as the first dates for distribution projects have yet to emerge and there are a number of projects receiving notifications after 2030.

Solar Media Market Research collected data on notifications, which projects have a Gate 2 Phase 1 or Phase 2 connection date, and what was pushed back purely due to the lack of infrastructure.

Let’s look at the three main distribution network operators (DNOs): National Grid (NGED), UK Power Networks (UKPN) and Northern Powergrid (NPG). 6,546 MW, 3,084.6 MW and 2,129.7 MW of Gate 2 Phase 1 tenders were distributed respectively.

Related:EirGrid identifies a shortage of energy capacity in Ireland between 2026 and 2028

National Grid network connection queue

With 4.5 GW operational and 6.5 GW allocated to phase 1, the network is 21% below the original target of 13.9 GW set by the National Energy System Operator (NESO) in 2024. The cutoff for Gate 2 Phase 1 offers appears to be around 500 in the queue, with notable projects such as Washdyke Solar Farm and Coven Solar Farm on the verge.

The difficulty arises because network constraints and reinforcement timelines play a large role in determining which projects receive Phase 1 bids. In the NGED region, there are several projects that were supposed to have Clause 1 protection and received Phase 2 bids even though they had a non-fixed date of 2027/28. This makes the assumptions much more complex and explains some of the reasons for the delays in the network reform process.

See also  Sheep and pigs are used for vegetation management on the Virginia solar project

Some grid delivery points (GSPs) were much busier than others. Iron Acton, Port Ham and Bicker Fen were at the top when it came to grid connection dates before 2031. Interestingly, none of these are at the top when it comes to pipeline, with Ratcliffe-on-Soar topping the charts with 500MW planned.

Queue for UK power networks

UKPN is perhaps the most complex DNO of them all. Of the 3.1 GW of Phase 1 offerings, Solar Media Market Research discovered 2.6 GW, and unsurprisingly two-thirds of this came from just nine GSPs. The lack of infrastructure in this region has been widely publicized and with the high CP30 target of 8.1 GW, the operational capacity of 2.6 GW and the 3.1 GW of phase 1, the network is almost 30% short.

Related:PACE 49.9MW solar power plant in Bedford approved

Once again technical limits played a major role in this, even more than NGED. Phase 2 offers went to 630 MW, with non-firm dates of 2027/28. Almost half of Rayleigh’s capacity falls into this category, while the GSP with the country’s largest pipeline, Bramford, at 150 MW, suffered the same fate.

In total, approximately 700 MW has been pushed back by the Transmission Operator (TO), but these projects still hope to connect before 2030.

UKPN was seen as a highly attractive region four to five years ago, with some developers having upwards of a dozen sites currently under planning or further development there. Some have now sold some of these sites: TotalEnergies’ purchase of Low Carbon included five projects in the area. Other developers have 5-6 sites with a total capacity of more than 150 MW that have only received Phase 2 bids.

See also  China's Catl launches new EV -Natrium battery

Northern Powergrid’s queue

While Northern Powergrid had the pipeline to meet targets, 4.9 GW is only planned; 2.1 GW received Phase 1 bids, and with approximately 600 MW operational in addition, we are once again far from the original target of 4.4 GW.

Unlike NGED, instead of the overall queue position, we have a queue position for each GSP.

Creyke Beck had a huge Gate 2 capacity connected to it, but much of this was in Phase 2, which mainly consisted of two major projects. Norton and Knaresborough had two of the largest Phase 1 pipelines, with Knaresborough at over 200 MW.

Related:Ampyr Solar Europe acquires East Yorkshire solar NSIP

The region is slightly less attractive than UKPN, and this is reflected in the developers and their pipeline. One developer has six locations of approximately 200 MW, almost half of which have a Phase 1 notification.

Figure 1: DNOs across England are under-delivering on Phase 1 offers, with transmission having to hold up excess capacity. While Northern Powergrid and UK Power Networks clearly had the pipeline, the phase 1 offers did not reflect this. Source: Solar Media Market Research.

Figure 1 shows projects that are in planning or further along, excluding anything still in the scoping or pre-consultation phase (some of which have received Phase 1 bids). What is striking is that the pipeline for UKPN and NPG is there, but because the infrastructure is not in place, the projects with non-firm dates in 2027/28 were postponed to 2032, with 1GW already identified.

With all but one DNO reaching the target, transmission projects were allocated the spare capacity, but these bring their own complexity and three of the short-term projects have already been postponed by two years.

See also  Panels on the roof, EV chargers and smart thermostats can shoot in to stimulate the resilience of the electricity grid

Mergers and acquisitions in the British solar market

More than forty solar parks before construction changed hands in 2025 and the first two months of 2026. The unprecedented activity is not expected to slow down anytime soon.

Downing has now bought five locations since Decemberindicating that the trades are dependent on expected gate offers. Another notable transaction was Uniper’s acquisition of several projects from Innova that went ahead 3 weeks ago.

Other developers took the plunge before the notifications were distributed and could pay the price with some receiving Phase 2 offers; it’s unclear if that was expected, or if the lack of acceleration came as a surprise.

For more information about projects that have received Gate 2 offers or to understand where the data comes from, please contact [email protected].



Source link

beginning Britain dates development emerge Energy fixed grid solar
Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
solarenergy
  • Website

Related Posts

8MSolar vs. Southern Energy Management: Which NC Solar Installer Is Right for You? (2026)

March 9, 2026

Key insights from the Italian trade fair Key Energy – SPE

March 9, 2026

WoodMac warns of a lithium supply shortage by 2028

March 9, 2026
Leave A Reply Cancel Reply

Don't Miss
Energy Storage

Investment of £1.56 million in solar energy with a higher return of 15%

By solarenergyNovember 7, 20250

Cambridge Photon Technology, a deep-tech spin-out from the University of Cambridge focusing on materials technology,…

Solargis updates software for design and evaluation of PV projects – SPE

January 23, 2025

Renewable energy sources will supply 71% of Portugal’s electricity by 2024, led by solar – SPE

January 4, 2025

New method to verify the warranty conditions of PV modules

May 22, 2025
Stay In Touch
  • Facebook
  • Twitter
  • Pinterest
  • Instagram
  • YouTube
  • Vimeo
Our Picks

8MSolar vs. Southern Energy Management: Which NC Solar Installer Is Right for You? (2026)

March 9, 2026

Fixed grid dates for solar energy development in Britain are beginning to emerge

March 9, 2026

Midsummer secures second order for CIGS production line equipment

March 9, 2026

‘Battery Atlas 2026’ maps European manufacturers of cells, batteries and batteries – SPE

March 9, 2026
Our Picks

8MSolar vs. Southern Energy Management: Which NC Solar Installer Is Right for You? (2026)

March 9, 2026

Fixed grid dates for solar energy development in Britain are beginning to emerge

March 9, 2026

Midsummer secures second order for CIGS production line equipment

March 9, 2026
About
About

Stay updated with the latest in solar energy. Discover innovations, trends, policies, and market insights driving the future of sustainable power worldwide.

Subscribe to Updates

Get the latest creative news and updates about Solar industry directly in your inbox!

Facebook X (Twitter) Instagram Pinterest
  • Contact
  • Privacy Policy
  • Terms & Conditions
© 2026 Tsolarenergynews.co - All rights reserved.

Type above and press Enter to search. Press Esc to cancel.