By ESS News
Return has launched construction works on the 100 MW / 200 MWH Antares Battery Energy Storage System (Bess) in Waddinxveen, in Western Netherlands. The project will go live in mid -2026 and play a crucial role in stabilizing the Dutch grid.
Once the assignment is given, the Antares project will be the first of the size that connects to the high-voltage network of Tennet Nederland.
Connecting to the Dutch high -voltage schedule is not normal sailing with more than 70 GW of customers, mainly large -scale storage projects for battery energy, which are currently stuck in the queue of the grid connection. In an attempt to tackle this, the operator of the transmission system was recently unlocked More than 9 GW high -voltage rast capacity By introducing flexible contracts for off-peak hours, also known as time-dependent transmission Right (TDTR) contracts.
Visit our visit ESS News website.
This content is protected by copyright and may not be reused. If you want to work with us and reuse part of our content, please contact: editors@pv-magazine.com.
Popular content