EPCG, the largest electricity provider in Montenegro, invests in two four -hour Bess to strengthen the resilience and balance of the grid and the balance.
Each system has a capacity of 30 MW and a storage capacity of 120 MWh, designed for operation at an output voltage of 35 kV. The batteries are installed on the site of the metal processing company EPCG željezara Nikšić.
The tender includes the full project range – including design, equipment offering, construction, commissioning, staff training and maintenance. Bidders must include two cost components in their offers. The first covers 10 years of services and maintenance to guarantee uninterrupted operation, while the second year covers 11 to 20, including replacement, upgrades and constant technical maintenance of important components.