Close Menu
  • News
  • Industry
  • Solar Panels
  • Commercial
  • Residential
  • Finance
  • Technology
  • Carbon Credit
  • More
    • Policy
    • Energy Storage
    • Utility
    • Cummunity
What's Hot

Fraunhofer ISE develops colored film technology for patterned solar panels

April 23, 2026

Thermoacoustic heat pumps are on the verge of commercial breakthrough – SPE

April 23, 2026

The federal court has halted Trump administration orders that hinder solar and wind energy development

April 23, 2026
Facebook X (Twitter) Instagram
Facebook X (Twitter) Instagram
Solar Energy News
Thursday, April 23
  • News
  • Industry
  • Solar Panels
  • Commercial
  • Residential
  • Finance
  • Technology
  • Carbon Credit
  • More
    • Policy
    • Energy Storage
    • Utility
    • Cummunity
Solar Energy News
Home - News - Balance Power to accelerate the 2036 grid connection for 99MW BESS
News

Balance Power to accelerate the 2036 grid connection for 99MW BESS

solarenergyBy solarenergySeptember 24, 2024No Comments3 Mins Read
Facebook Twitter Pinterest LinkedIn Tumblr Email
Share
Facebook Twitter LinkedIn Pinterest Email
The BESS will provide grid stabilizing functions. Image: Balance power.

Energy developer Balance Power has today (September 24) received planning permission for a 99MW/99MWh battery energy storage system (BESS) at Iron Acton, south Gloucestershire.

Balance Power is still finalizing the construction timeline for the 1-hour BESS, but stressed that the company has ongoing discussions with National Grid to extend the date for connection to the 100MW grid, which is currently set for June 2036. to advance.

The BESS, located approximately ten miles northeast of Bristol, will ensure stability to the electricity grid by supplying energy during periods of peak demand. Balance Power confirmed that the stored energy would be renewable, contributing to the wider decarbonisation of the electricity grid.

The Iron Acton Grid Supply Point (GSP) network currently has 120 MW of solar PV and wind connected, with a further 750 MW of solar PV connections planned.

Oliver Pettersen, connections manager at Balance Power, stated that the project will be “critical” in managing the excess energy generation produced by the variable renewable energy generation projects in the area.

“With the extensive development of solar energy in the Iron Acton area, this project will be critical for managing excess energy generation and more broadly for balancing renewable energy supply and demand, reducing dependence on fossil fuels” , said Pettersen.

“Due to the size and scale of the project, it also marks a major step forward for the UK’s transition to net zero, which relies on battery storage projects providing stability for a carbon-free electricity grid. We are grateful for the support from South Gloucestershire and the community. It is thanks to our collective efforts and close collaboration that we have achieved this fantastic result.”

See also  Solar Panels and Power for Small Businesses (2026)

The planning approval for the BESS comes as Balance Power recently secured a £5.1 million debt facility from investment manager Triple Point to boost Balance’s solar PV and BESS pipeline. Part of the funding was used to acquire the 6MWp Roborough project from Regener8 Power, based in Plymouth, Devon.

Grid connections continue to dampen net zero ambitions

Several countries have experienced problems with their grid connection queues as many new renewable energy projects are brought online, and Britain is no exception. According to ESO, the queue for transmission connections has grown by more than 275 GW since October 2022 and by an average of more than 20 GW per month over the past twelve months.

This recently resulted in market consultancy’s Cornwall Insight brand receiving timely grid connections as the “biggest challenge in the rollout of renewable energy in Britain”.

The ESO also expects that the total queue, for both transmission and distribution, is likely to exceed 800 GW by the end of 2024, more than four times the installed capacity that the organization estimates will be needed in 2050.

This is why ESO made the proposal ‘First ready, first connected’ approach for new requests and existing projects in the queue.

ESO proposed a two-step process for new applications, with an annual application window to reach ‘Gate 1’ and ‘readiness’ criteria to reach ‘Gate 2’. Only projects that meet the Gate 2 criteria will be queued.

The long-term connection reforms were first announced in December 2023 and would have only applied to new connection requests and significant change requests received from January 2025 onwards.

See also  Store excess PV power with electric heat storage boilers

Source link

99MW accelerate Balance BESS connection grid power
Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
solarenergy
  • Website

Related Posts

Rongke Power introduces 2 MW/8 MWh vanadium flow battery storage system – SPE

April 21, 2026

Jinko Power starts data center activities with 1 GW project in China – SPE

April 20, 2026

Ofgem, DESNZ issue update on grid connection, BESS concerned about oversupply

April 20, 2026
Leave A Reply Cancel Reply

Don't Miss
Solar Industry

Back-contact VIPV modules based on fiber optic composite blades

By solarenergyMarch 17, 20250

A university team in Poland has developed lightweight bifacial vehicle integrated PV (VIPV) mini modules…

Microsoft Investing in 100 MW Solar Port Folio for disadvantaged communities in Arkansas, Louisiana

March 2, 2025

ProScore launches IRA compliance software

November 22, 2024

Quinbrook-backed EOS to deliver BESS at Teesworks Freeport

July 2, 2024
Stay In Touch
  • Facebook
  • Twitter
  • Pinterest
  • Instagram
  • YouTube
  • Vimeo
Our Picks

Fraunhofer ISE develops colored film technology for patterned solar panels

April 23, 2026

Thermoacoustic heat pumps are on the verge of commercial breakthrough – SPE

April 23, 2026

The federal court has halted Trump administration orders that hinder solar and wind energy development

April 23, 2026

Zendure launches battery ranges for residential PV – SPE

April 23, 2026
Our Picks

Fraunhofer ISE develops colored film technology for patterned solar panels

April 23, 2026

Thermoacoustic heat pumps are on the verge of commercial breakthrough – SPE

April 23, 2026

The federal court has halted Trump administration orders that hinder solar and wind energy development

April 23, 2026
About
About

Stay updated with the latest in solar energy. Discover innovations, trends, policies, and market insights driving the future of sustainable power worldwide.

Subscribe to Updates

Get the latest creative news and updates about Solar industry directly in your inbox!

Facebook X (Twitter) Instagram Pinterest
  • Contact
  • Privacy Policy
  • Terms & Conditions
© 2026 Tsolarenergynews.co - All rights reserved.

Type above and press Enter to search. Press Esc to cancel.