Close Menu
  • News
  • Industry
  • Solar Panels
  • Commercial
  • Residential
  • Finance
  • Technology
  • Carbon Credit
  • More
    • Policy
    • Energy Storage
    • Utility
    • Cummunity
What's Hot

Origis is developing a 413 MW solar portfolio in West Texas

March 6, 2026

New Jersey expands state community solar program by 3 GW

March 6, 2026

How to address imbalance datasets in solar panel dust detection

March 5, 2026
Facebook X (Twitter) Instagram
Facebook X (Twitter) Instagram
Solar Energy News
Friday, March 6
  • News
  • Industry
  • Solar Panels
  • Commercial
  • Residential
  • Finance
  • Technology
  • Carbon Credit
  • More
    • Policy
    • Energy Storage
    • Utility
    • Cummunity
Solar Energy News
Home - Energy Storage - Ofgem supports a fine for slow-moving projects in the queue
Energy Storage

Ofgem supports a fine for slow-moving projects in the queue

solarenergyBy solarenergyOctober 21, 2025No Comments3 Mins Read
Facebook Twitter Pinterest LinkedIn Tumblr Email
Share
Facebook Twitter LinkedIn Pinterest Email

Developers have until November 3 to respond to Ofgem’s ‘minded’ position to approve a Progression Commitment Fee (PCF) as part of the reformed grid connection process.

The plans that Ofgem wants to approve will see projects that accept a Gate 2 offer but fail to meet Queue Management Milestone 1, namely initiating planning permission, pay the PCF. Treated as a cancellation fee, the PCF would start at £2,500/MW and increase by £2,500/MW for every six months that a project does not progress, up to a maximum of £10,000/MW.

The National Energy System Operator (NESO) has proposed an amendment to the Connection and Use of System Code (CUSC). introduces the PCF in February as part of being grid connection queuing reforms.

It would be a way to ensure that the grid queue keeps moving after the reforms are implemented. Projects are required to provide protection against the PCF until they reach M1.

The regulator’s main reasons for approving the change to the code are that it will improve queuing efficiency by encouraging timely termination of less committed projects, ‘strengthen’ competition in electricity generation and supply and ultimately ‘ensure a ‘healthy’, efficient and competitive connection queue that is in line with the objectives of CP2030.

However, it’s not a move that many are likely to be happy with. Earlier this year, when Ofgem approved NESO’s grid connection queue review, many developers said they felt the decision was hasty and would disadvantage some projects. creating “winners and losers”.

Related:Lime Down Solar’s 500MW/1GWh solar-plus-storage DCO accepted by PINS

While some solar developers were cautiously supportive of the reforms, much of that goodwill has disappeared as the process has gotten underway. First the application portal for Gate 2 connections experienced “many usability issues”keeping the window open longer and granting a reprieve when projects would receive connection offers.

See also  Sicily opens €246 million tender for solar and battery storage projects of all sizes under new EU-focused program – SPE

The timeline for Gate 2 offerings has been pushed since then, now with developers to find out in December whether they have a connection.

As Solar Media’s Market Research solar analyst Josh Cornes wrote in a blog post Solar energy portalhave transmission-scale solar PV developers taken enormous risks over the past five yearswith millions being spent to secure grid connection offers for solar projects.

If developers wait until the announcement date for their network offerings, anyone who gets connections before 2029 simply won’t have enough time to go through the prerequisites process and construction to meet the commercial operation date (COD) that NESO assigns them.

The additional pressure of the PCF adds a new layer to this financial risk. However, it is worth noting that when NESO submitted the code change proposal, director of its liaison program Matt Vickers wrote that the additional requirement will only be triggered if projects in the early stages of the Gate 2 queue do not progress as expected “and if there are still too many non-viable projects that hinder the progress of others without being replaced by suitable alternatives.”

Related:Beyond the panels: how solar farms drive net benefits for biodiversity

If a ‘trigger point’ is not reached, the PCF may never activate. Consultation documents and form to respond available from Ofgem here.



Source link

Fine ofgem projects queue slowmoving supports
Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
solarenergy
  • Website

Related Posts

Zelestra continues construction of two Texas projects

March 5, 2026

EirGrid identifies a shortage of energy capacity in Ireland

March 5, 2026

China’s 600 MW/2.4 GWh storage facility will be the world’s largest CAES site – SPE

March 4, 2026
Leave A Reply Cancel Reply

Don't Miss
Policy

‘We need male allies who understand that inclusivity benefits everyone’ – SPE

By solarenergyNovember 8, 20250

The 2025 IRENA report shows that women represent only 32% of the renewable energy workforce,…

Prosperity Works, Chaberton Energy Start Work at 2.8 MW New Mexico Community Solar Project

January 28, 2025

EnergyAid offers lifeline on abandoned suntuity solar customers

June 3, 2025

Vehicle-integrated photovoltaic solar energy for biofuel transport trucks – SPE

October 9, 2025
Stay In Touch
  • Facebook
  • Twitter
  • Pinterest
  • Instagram
  • YouTube
  • Vimeo
Our Picks

Origis is developing a 413 MW solar portfolio in West Texas

March 6, 2026

New Jersey expands state community solar program by 3 GW

March 6, 2026

How to address imbalance datasets in solar panel dust detection

March 5, 2026

Oleic acid anti-pollution coating for solar panels – SPE

March 5, 2026
Our Picks

Origis is developing a 413 MW solar portfolio in West Texas

March 6, 2026

New Jersey expands state community solar program by 3 GW

March 6, 2026

How to address imbalance datasets in solar panel dust detection

March 5, 2026
About
About

Stay updated with the latest in solar energy. Discover innovations, trends, policies, and market insights driving the future of sustainable power worldwide.

Subscribe to Updates

Get the latest creative news and updates about Solar industry directly in your inbox!

Facebook X (Twitter) Instagram Pinterest
  • Contact
  • Privacy Policy
  • Terms & Conditions
© 2026 Tsolarenergynews.co - All rights reserved.

Type above and press Enter to search. Press Esc to cancel.