Close Menu
  • News
  • Industry
  • Solar Panels
  • Commercial
  • Residential
  • Finance
  • Technology
  • Carbon Credit
  • More
    • Policy
    • Energy Storage
    • Utility
    • Cummunity
What's Hot

Fraunhofer ISE develops colored film technology for patterned solar panels

April 23, 2026

Thermoacoustic heat pumps are on the verge of commercial breakthrough – SPE

April 23, 2026

The federal court has halted Trump administration orders that hinder solar and wind energy development

April 23, 2026
Facebook X (Twitter) Instagram
Facebook X (Twitter) Instagram
Solar Energy News
Thursday, April 23
  • News
  • Industry
  • Solar Panels
  • Commercial
  • Residential
  • Finance
  • Technology
  • Carbon Credit
  • More
    • Policy
    • Energy Storage
    • Utility
    • Cummunity
Solar Energy News
Home - Energy Storage - Ofgem supports a fine for slow-moving projects in the queue
Energy Storage

Ofgem supports a fine for slow-moving projects in the queue

solarenergyBy solarenergyOctober 21, 2025No Comments3 Mins Read
Facebook Twitter Pinterest LinkedIn Tumblr Email
Share
Facebook Twitter LinkedIn Pinterest Email

Developers have until November 3 to respond to Ofgem’s ‘minded’ position to approve a Progression Commitment Fee (PCF) as part of the reformed grid connection process.

The plans that Ofgem wants to approve will see projects that accept a Gate 2 offer but fail to meet Queue Management Milestone 1, namely initiating planning permission, pay the PCF. Treated as a cancellation fee, the PCF would start at £2,500/MW and increase by £2,500/MW for every six months that a project does not progress, up to a maximum of £10,000/MW.

The National Energy System Operator (NESO) has proposed an amendment to the Connection and Use of System Code (CUSC). introduces the PCF in February as part of being grid connection queuing reforms.

It would be a way to ensure that the grid queue keeps moving after the reforms are implemented. Projects are required to provide protection against the PCF until they reach M1.

The regulator’s main reasons for approving the change to the code are that it will improve queuing efficiency by encouraging timely termination of less committed projects, ‘strengthen’ competition in electricity generation and supply and ultimately ‘ensure a ‘healthy’, efficient and competitive connection queue that is in line with the objectives of CP2030.

However, it’s not a move that many are likely to be happy with. Earlier this year, when Ofgem approved NESO’s grid connection queue review, many developers said they felt the decision was hasty and would disadvantage some projects. creating “winners and losers”.

Related:Lime Down Solar’s 500MW/1GWh solar-plus-storage DCO accepted by PINS

While some solar developers were cautiously supportive of the reforms, much of that goodwill has disappeared as the process has gotten underway. First the application portal for Gate 2 connections experienced “many usability issues”keeping the window open longer and granting a reprieve when projects would receive connection offers.

See also  A tender has been opened for PV-powered pump irrigation projects in the Philippines

The timeline for Gate 2 offerings has been pushed since then, now with developers to find out in December whether they have a connection.

As Solar Media’s Market Research solar analyst Josh Cornes wrote in a blog post Solar energy portalhave transmission-scale solar PV developers taken enormous risks over the past five yearswith millions being spent to secure grid connection offers for solar projects.

If developers wait until the announcement date for their network offerings, anyone who gets connections before 2029 simply won’t have enough time to go through the prerequisites process and construction to meet the commercial operation date (COD) that NESO assigns them.

The additional pressure of the PCF adds a new layer to this financial risk. However, it is worth noting that when NESO submitted the code change proposal, director of its liaison program Matt Vickers wrote that the additional requirement will only be triggered if projects in the early stages of the Gate 2 queue do not progress as expected “and if there are still too many non-viable projects that hinder the progress of others without being replaced by suitable alternatives.”

Related:Beyond the panels: how solar farms drive net benefits for biodiversity

If a ‘trigger point’ is not reached, the PCF may never activate. Consultation documents and form to respond available from Ofgem here.



Source link

Fine ofgem projects queue slowmoving supports
Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
solarenergy
  • Website

Related Posts

Thermoacoustic heat pumps are on the verge of commercial breakthrough – SPE

April 23, 2026

Low-pressure hydrogen bridges seasonal gaps in Japanese solar-powered buildings – SPE

April 22, 2026

Ofgem unveils reforms to strengthen consumer protection

April 22, 2026
Leave A Reply Cancel Reply

Don't Miss
Utility

Amazon signs PPA for full capacity of 100-MW Mississippi Solar Project

By solarenergyFebruary 20, 20250

EDP ​​Renewable energy sources North -America has launched his Ragsdale Solar Park in Madison Country,…

Green Lantern Solar turns gravel pit into 500 kW solar project

January 16, 2025

Solar Powered Robotics (2025) | 8MSolar

July 31, 2025

Maldives tenders up to 150 MW Zonne -Zon – PV Magazine International

February 11, 2025
Stay In Touch
  • Facebook
  • Twitter
  • Pinterest
  • Instagram
  • YouTube
  • Vimeo
Our Picks

Fraunhofer ISE develops colored film technology for patterned solar panels

April 23, 2026

Thermoacoustic heat pumps are on the verge of commercial breakthrough – SPE

April 23, 2026

The federal court has halted Trump administration orders that hinder solar and wind energy development

April 23, 2026

Zendure launches battery ranges for residential PV – SPE

April 23, 2026
Our Picks

Fraunhofer ISE develops colored film technology for patterned solar panels

April 23, 2026

Thermoacoustic heat pumps are on the verge of commercial breakthrough – SPE

April 23, 2026

The federal court has halted Trump administration orders that hinder solar and wind energy development

April 23, 2026
About
About

Stay updated with the latest in solar energy. Discover innovations, trends, policies, and market insights driving the future of sustainable power worldwide.

Subscribe to Updates

Get the latest creative news and updates about Solar industry directly in your inbox!

Facebook X (Twitter) Instagram Pinterest
  • Contact
  • Privacy Policy
  • Terms & Conditions
© 2026 Tsolarenergynews.co - All rights reserved.

Type above and press Enter to search. Press Esc to cancel.